MEMBER SIGN IN
Not a member? Become one today!
         iBerkshires     Berkshire Chamber     MCLA     City Statistics    
Search
North Adams Airport Hangar Still Unfinished
Jack Guerino, iBerkshires Staff
06:00PM / Friday, February 23, 2024
Print | Email  

The North East Hangar project has been funded since 2022 but post-pandemic delays have significantly pushed out the completion date.

NORTH ADAMS, Mass. — Without electricity, the newly renovated North East hangar remains incomplete, although airport engineers hope to bring service to the city hangar in the coming months.
 
"We are kind of at a standstill, and we have been at a standstill probably two months now," Stantec Engineer Peter Enzien told the commission Tuesday.
 
Enzien, who is the airport's contracted engineer, said the city is waiting on National Grid to complete a redesign of the new service entrance to the building. Initial designs were too similar to original designs that were deemed unsatisfactory. 
 
National Grid had planned to pull power from an existing transformer some 70 feet away from the hangar, but it was agreed that said transformer was too old to handle the extra load. Also, there were questions about the utility pole which held the transformer. The pole would need to be replaced, however the city did not budget for this expense.
 
"It was a lot more than we were carrying in the cost of the project just to bring new service to the hangar," Enzien said.
 
A new design will draw power from a more appropriate source in the airport. A midspan pole will have to be installed to support the line.
 
In 2022, the commissioners voted to go forward with the renovation of the derelict hangar, purchased by the city. The project would tap a mix of state, federal, and local funds.
 
The project has been delayed a few times due to post-pandemic supply shortages, long shipping waits and price increases.
 
As it stands, Enzien said the hangar is essentially complete but electricity is needed to truly close the project out.
 
"When we have electricity we will be able to test the door and make adjustments. There are a few punch list items they need to finish up," he said. "That essentially will be the end of the project. We are about 90 percent done."
 
But this final step will still take time. National Grid must issue a service agreement that has to be accepted by the city. Then it is handed off to the contractor for implementation. 
 
The most recent completion date was this summer, but Enzien was hesitant to throw out a new date without having the agreement in hand. 
 
Enzien also discussed some possible remedies for reported low flying aircraft.
 
In the fall of 2023, some residents east of the airport aired their concerns about an uptick in planes flying uncomfortably close to their homes.
 
At the meeting, Enzien told residents that in reality the planes landing on runway 29 were landing properly now that some trees had been cut down. The trees impeded the correct landing and approach and now, planes are landing a little bit lower.
 
The commission asked Airport Manager Bruce Goff to post on various pilot forums about the approach so pilots know to take care when landing.
 
On Tuesday, Enzien ruled out the installation of a precision approach path indicator (PAPI) system. 
 
A PAPI is a system of lights on the side of a runway threshold that provides visual descent guidance information during an aircraft's final approach.
 
He said after an analysis it was found that with mountains and terrain, there are too many obstacles in place for the PAPI to be effective.
 
He said the installation of a beacon could potentially be helpful but this is something the FAA would need to approve.
 
Goff did note that the posts he has made are still circulating and will continue to do so.
 
0Comments
More Featured Stories
NorthAdams.com is owned and operated by: Boxcar Media 102 Main Sreet, North Adams, MA 01247 -- T. 413-663-3384
© 2011 Boxcar Media LLC - All rights reserved